The Hanson Memorial Parking Structure Restoration project is now underway. The work will take place throughout all levels of the building, and will include efforts such as routine structural maintenance, repainting, replacement of waterproofing materials, and upgrades to the building mechanical/electrical systems. The work is planned to begin the first week of February 2024 and conclude in July 2025.
The work will be completed in phases to allow the building to remain open to public parking for the duration of the project. Between October 20th and up to November 30th, 47 parking spaces will be available on the ground level parking only. Beyond that it is anticipated that no more than 50% of the 271 available parking spaces will be closed at any time. There is also parking availability at the Chown Memorial and Robert Bruce Memorial parking garages in the two adjacent blocks to the west.
Other Delays